![Mercedes Benz Türk A.Ş. Hoşdere Facilities](/Files/Images/Content/103947f3-b69a-4a3f-9888-43af424f0d0d/1.jpg)
MERCEDES BENZ TÜRK A.Ş. HOŞDERE FACİLİTİES
Name Of Project: MERCEDES BENZ TÜRK A.Ş. HOŞDERE FACILITIES (A 12 CELLED, DOUBLE BUS BARRED DİSTRİBUTİON CENTER AND DİSTRİBUTİON CENTER AUTOMATİC TRANSFER SYSTEM)
LOCATION OF THE PROJECT: HOŞDERE – HADIMKÖY- İSTANBUL
START DATE: 01.08.1993
COMPLETION DATE: 01.12.1995
![](/Files/Images/Content/bd2a8929-67ac-4731-9bdb-391f4ab94a51/1.jpg)
![](/Files/Images/Content/d4225063-2e86-4946-9961-1fa1fe205127/2.jpg)
![İkitelli Başak Housing Units](/Files/Images/Content/6d82e575-ea96-4bf9-b97e-e91893566db6/s1.jpg)
İkitelli Başak Housing Units
Name Of Project: İkitelli Başak Housing Units (1. Stage Medium Voltage-Low Voltage Transformer and Distribution Network and Street Lighting Works
LOCATION OF THE PROJECT: İKİTELLİ- İSTANBUL
START DATE: 06.06.1996
COMPLETION DATE: 24.09.1996
![](/Files/Images/Content/b2001a19-1afb-4617-9143-81d1225e132d/s1.jpg)
![Kağıthane Başak Collective Housing](/Files/Images/Content/639d7858-cbd3-42b7-aaf8-43b02ec1ea02/kalitesiz-1.jpg)
KAĞITHANE BAŞAK COLLECTİVE HOUSİNG
Name Of Project: KAĞITHANE BAŞAK COLLECTIVE HOUSING (1. STAGE MEDİUM VOLTAGE – LOW VOLTAGE TRANSFORMER AND DİSTRİBUTİON NETWORK AND STREET LİGHTİNG WORK)
LOCATION OF THE PROJECT: KAĞITHANE- İSTANBUL
START DATE: 15.10.1996
COMPLETION DATE: 25.12.1996
![](/Files/Images/Content/2fa521b2-db1d-49b7-91ca-4430abf9aedb/kalitesiz-1.jpg)
![](/Files/Images/Content/d2b4c0ca-8e5d-4ee2-a2ed-96e4227c083e/kalitesiz-2.jpg)
![Pendik Hilal Collective Housing](/Files/Images/Content/1085704d-2721-43a3-87ed-53cbf16d781b/s1.jpg)
Pendik Hilal Collective Housing
Name Of Project: Pendik Hilal Collective Housing (1. Stage Medium Voltage-Low Voltage Transformer and Distribution Network and Street Lighting Works)
LOCATION OF THE PROJECT: PENDİK- İSTANBUL
START DATE: 18.03.1997
COMPLETION DATE: 14.08.1997
![](/Files/Images/Content/b99d29b5-e5e9-443d-8ad3-f321b669c362/s1.jpg)
![Fair And Exhibition Center](/Files/Images/Content/d02f77b3-5423-493a-8857-59d1e50deaf7/1.jpg)
Fair And Exhibition Center
Name Of Project: FAIR AND EXHIBITION CENTER(16 Celled 34.5 Kw distribution center)
LOCATION OF THE PROJECT: YEŞİLKÖY- İSTANBUL
START DATE: 21.11.1997
COMPLETION DATE: 24.02.1998
![](/Files/Images/Content/f8dc2842-0498-401a-9cb9-40dfc9db9b66/1.jpg)
![İkitelli Başak Housing Units Power Transmission Line Works](/Files/Images/Content/3403b531-3e5d-4070-b5f6-62584e2874d7/1.jpg)
İkitelli Başak Housing Units Power Transmission Line Works
Name Of Project: İkitelli Başak Housing Units (4. Stage Medium Voltage-Low Voltage Transformer and Distribution Network and Street Lighting Work- Power Transmission Line Displacement Works)
LOCATION OF THE PROJECT: İKİTELLİ- İSTANBUL
START DATE: 26.01.1999
COMPLETION DATE: 02.01.2001
![](/Files/Images/Content/48a76315-d65f-4b94-912e-09888386fb65/1.jpg)
![İkitelli Başak Housing Units Transformer Center](/Files/Images/Content/ff6cdbc3-5724-4c8d-a3b6-1731e6c5c9f1/s1.jpg)
İkitelli Başak Housing Units Transformer Center
Name Of Project: İkitelli Başak Housing Units (4. Stage 2. Section Medium Voltage-Low Voltage Transformer Centers & Distribution Network and Türk Telekom Transformer Center Construction Works)
LOCATION OF THE PROJECT: İKİTELLİ- İSTANBUL
START DATE: 21.05.2001
COMPLETION DATE: 30.06.2002
![](/Files/Images/Content/df880051-0445-4343-bdf7-e8a7695e8858/s1.jpg)
![Pendik Aydos Hilal Collective Housing](/Files/Images/Content/0fc4d528-5aee-4626-85d6-db483ba6d925/s1.jpg)
Pendik Aydos Hilal Collective Housing
Name Of Project: Pendik Aydos Hilal Collective Housing (Medium Voltage-Low Voltage Transformer Centers & Distribution Network and Construction Works)
LOCATION OF THE PROJECT: AYDOS - PENDİK- İSTANBUL
START DATE: 26.06.2002
COMPLETION DATE: 03.12.2003
![](/Files/Images/Content/2411ede8-2df7-4bfc-a8c5-cc7ca5443801/s1.jpg)
![İkitelli Başak Housing Units 5th Stage-1st Section](/Files/Images/Content/b62845e4-1175-433b-a398-8bd02314853c/1.jpg)
İkitelli Başak Housing Units 5th Stage-1st Section
Name Of Project: İkitelli Başak Housing Units (The Construction, Infrastructure and Landscaping Works & MV/LV Electrical Infrastructure Works of 216 Units in the 5th Stage 1st Section 2nd Region to be Carried Out with Revenue Sharing Method)
LOCATION OF THE PROJECT: İKİTELLİ- İSTANBUL
START DATE: 22.11.2004
COMPLETION DATE: 04.04.2006
![](/Files/Images/Content/1cbe0a32-274e-4e8d-a9b1-303d22097cf3/1.jpg)
![](/Files/Images/Content/d4043de9-3783-4541-a06d-ab88ae64efff/2.jpg)
![](/Files/Images/Content/4bd2519b-96c4-4b40-a29b-7501da6bfaca/3.jpg)
![Akpınar Industrial Complex](/Files/Images/Content/8f70269d-c1d3-47e1-87e6-a2828eea2c47/1-.jpg)
AKPINAR INDUSTRIAL COMPLEX
Name Of Project: MV Cable Network Distribution and Transformer Center Lighting Facility Works
LOCATION OF THE PROJECT: AKPINAR – HADIMKÖY - ISTANBUL
START DATE: 01.06.2006
COMPLETION DATE: 31.12.2007
![](/Files/Images/Content/b796ed08-cad4-40f1-a5df-17a37c7cd251/1-.jpg)
![Lighting Works on Historical Assets](/Files/Images/Content/ab726950-0ac9-4cf1-b779-cd6a12448292/s1.jpg)
Lighting Works on Historical Assets
Name Of Project: Lighting Works on Historical Assets Throughout Istanbul
LOCATION OF THE PROJECT: ISTANBUL
START DATE: 17.03.1998
COMPLETION DATE: 28.08.1998
YEDİKULE WALLS – ORTAKÖY MOSQUE -BEYAZIT MOSQUE – BEYLERBEYİ MOSQUE -PİYALEPAŞA MOSQUE – DOLMABAHÇE MOSQUE KILIÇ ALİ PAŞA MOSQUE – VALİDE SULTAN MOSQUE -AYAZMA MOSQUE – YAHYA EFENDİ MOSQUE -EMİRGAN MOSQUE – ŞEHZADE BAŞI MOSQUE -CİHANGİR MOSQUE – SOKULLU MEHMET PAŞA MOSQUE -MURAT PAŞA MOSQUE – NUSRETİYE MOSQUE MİHRİMAH SULTAN MOSQUE – MOLLA FENARİ İSA MOSQUE -MOLLA ZEYREK MOSQUE
![](/Files/Images/Content/c69e2d72-8176-492a-b2be-79fa9edeb2f1/s1.jpg)